Waarschuwingssignaal · gecontroleerd door CrowdinformLendopolisGroene energieRisico'sWacht op antwoord
Lendopolis: EUR 5m project late, 24 projects in collective proceedings, 48 final losses (17 Nov 2026)
Our check:
- Lendopolis's performance figures, updated on 17 November 2026, show 1 project 0-6 months late with EUR 5,000,000 outstanding.
- 24 projects are in collective proceedings with EUR 1,633,482 outstanding, and 48 projects are recorded as final losses with EUR 3,076,500 written off.
- Why it matters: one late project of EUR 5,000,000 is large for a single loan. The platform has funded EUR 456,068,066 in total and shows an internal rate of return of 6.20% after losses.
- What it is not: a late payment is not a loss; the figures above are totals over all years, as shown on the page.
Checked by Crowdinform on 17 November 2026. The platform can reply here.
Onze bronnen
Een door Crowdinform gecontroleerd waarschuwingssignaal: de tekst hierboven is onze controle, met de reactie van het platform als dat reageerde. Deel hieronder je eigen ervaring; alleen feiten en data.